Instruction of changes to standards below
Track Work Instruction (3B014) - How to prepare track for the ballast regulating with On-Track Machine (OTM) Issue 2
Changes:
-
Added to the title: ‘with an On-Track Machine (OTM)’
-
Updated photo to a currently used ballast Regulating OTM
-
Corrected ‘TWI 2P045’ to TWI 2P009, Which is the correct document reference for ‘How to maintain rail flange lubricator’
-
Added ‘ Competence’ section
-
Re-worded the method section
-
Highlighted in the ‘Record’ section, to record data into Ellipse
Track Work Instruction (3B016) - How to regulate ballast by machine Issue 2
Changes:
-
Added more, and current photos of OTM Ballast Regulators
-
Added ‘ Competence’ section
-
Added more substance to the risk section
-
Re-worded the method section
-
Added the ‘Remember’ section
If you have any questions regarding the updates, please leave your questions in the comments section and we will ensure you are contacted promptly.