The Network Rail Standards Issue 130, have been reviewed and the below change is required to Using On Track Plant for flailing operations.
NR/L3/MTC/RCS0216 Risk Control Manual Issue 28 - Compliance Date 02/03/2024
RCS NO.: NR/L3/MTC/RCS0216/MP13 Issue: 3
MP13 Using OTP for flailing operations
•Key risks titles changed/amended or removed.
•Referenced TRCS descriptions amended throughout.
•All sections have been updated to give greater clarity.
•All sections have been updated to bring the TRCS into line with latest task and equipment requirements.